The most complete case: strong grid capacity close to the substation, a signed letter of intent and support recorded in the council's planning minutes. The open point is money: the owner requests a 12% revenue share. Confirm whether acceptable terms have been agreed.
Full breakdown
Spare grid capacity30 / 30
4.6 MW
Grid operator, as of 2026-06-30
Distance to substation15 / 15
0.8 km
Grid operator, as of 2026-06-30
Landowner20 / 20
Letter of intent signed
Team's site tracker, note of 2026-08-19
Owner signed the letter of intent. Wants 12% revenue share.
Council and neighbours10 / 10
Supportive
Field note, 2026-09-03
Council planning committee minutes record support for local storage on this plot.
Flood risk12 / 15
Low
Land registry record, 2025-09-12
Usable land10 / 10
2,100 m²
Land registry record, 2025-09-12
297/100
Grelle Harbour Plot
S-018 · Nordholm
Matches Kessby on grid capacity and distance, with a signed letter of intent and council committee support. No additional conditions are recorded in the supplied notes. Nordholm reports grid figures in kilowatts; we converted them, and it's worth a quick confirmation with the operator.
Full breakdown
Spare grid capacity30 / 30
4.6 MW
Grid operator, as of 2026-06-30
Distance to substation15 / 15
0.8 km
Grid operator, as of 2026-06-30
Landowner20 / 20
Letter of intent signed
Team's site tracker, note of 2026-08-10
Owner signed the letter of intent.
Council and neighbours10 / 10
Supportive
Field note, 2026-08-12
Council planning committee minutes record support for local storage on this plot.
Flood risk12 / 15
Low
Land registry record, 2025-11-03
Usable land10 / 10
1,700 m²
Land registry record, 2025-11-03
396/100
Brekke Depot
S-017/S-031 · Sveld
Plenty of grid capacity, no flood zone recorded in the registry and a signed letter of intent. Neighbours were indifferent: no support recorded, and no opposition recorded either. The team logged it twice under two names; both entries are combined here.
Full breakdown
Spare grid capacity30 / 30
4.7 MW
Grid operator, as of 2026-06-30
Distance to substation15 / 15
0.9 km
Grid operator, as of 2026-06-30
Landowner20 / 20
Letter of intent signed
Team's site tracker, note of 2026-09-08
Owner signed the letter of intent. (Brekke depot, finally.)
Council and neighbours6 / 10
Neutral
Field note, 2026-07-02
Neighbours we spoke to were indifferent.
Flood risk15 / 15
No flood zone recorded
Land registry record, 2025-11-03
Usable land10 / 10
1,800 m²
Land registry record, 2025-11-03
493/100
Varne Farm Edge
S-027 · Tarrow
Check: noise report
The best grid connection of the five and a signed letter of intent. The council has no position yet: its support depends on the noise report. Confirm the report's status and outcome.
Full breakdown
Spare grid capacity30 / 30
5.5 MW
Grid operator, as of 2026-06-30
Distance to substation15 / 15
0.5 km
Grid operator, as of 2026-06-30
Landowner20 / 20
Letter of intent signed
Team's site tracker, note of 2026-07-30
Owner signed the letter of intent.
Council and neighbours6 / 10
Neutral
Field note, 2026-08-21
Council has no formal position yet; officer said 'depends on the noise report'.
Flood risk12 / 15
Low
Land registry record, 2025-11-03
Usable land10 / 10
1,400 m²
Land registry record, 2025-11-03
586/100
Orlund Depot Yard
S-014 · Sveld
Check: owner agreement
Good grid capacity, no flood zone recorded in the registry and a ward councillor openly in favour. It ranks fifth because the owner is still at heads of terms with no letter of intent yet, and the cable run is a little longer.
Full breakdown
Spare grid capacity30 / 30
4.1 MW
Grid operator, as of 2026-06-30
Distance to substation9 / 15
1.4 km
Grid operator, as of 2026-06-30
Landowner12 / 20
In talks, no letter of intent yet
Team's site tracker, note of 2026-09-11
Good first call with the owner, sending heads of terms.
Council and neighbours10 / 10
Supportive
Field note, 2026-08-02
Met the ward councillor; she is openly in favour and offered to speak at the hearing.
Flood risk15 / 15
No flood zone recorded
Land registry record, 2025-11-03
Usable land10 / 10
1,600 m²
Land registry record, 2025-11-03
Why not these
Esk Mill Land
100/100
S-009 · would score this if it weren't excluded
Left out: possible nature reserve
On paper it's the best site. But a field note says part of the plot is inside a protected nature reserve. The reserve boundary needs verification before the site can be reconsidered. We can't build in a reserve, so it stays excluded until then.
Municipal ecologist says the northern third of the plot falls inside the Esker Meadows reserve designated in 2024.Full breakdown
Spare grid capacity30 / 30
4.9 MW
Grid operator, as of 2026-06-30
Distance to substation15 / 15
0.7 km
Grid operator, as of 2026-06-30
Landowner20 / 20
Letter of intent signed
Team's site tracker, note of 2026-07-14
Owner signed the letter of intent. Owner very keen.
Council and neighbours10 / 10
Supportive
Field note, 2026-08-05
Met the ward councillor; she is openly in favour and offered to speak at the hearing.
Flood risk15 / 15
No flood zone recorded
Land registry record, 2018-04-20
Usable land10 / 10
2,600 m²
Land registry record, 2018-04-20
Rook Street Plot
82/100
S-013
Left out: plot too small
The land registry says 2,400 m², but that record is from 2017. A recent field note says half was sold and only about 700 m² remains. A 2 MW battery needs about 1,200 m².
roughly 700 m² remainsFull breakdown
Spare grid capacity30 / 30
4.3 MW
Grid operator, as of 2026-06-30
Distance to substation15 / 15
0.9 km
Grid operator, as of 2026-06-30
Landowner12 / 20
In talks, no letter of intent yet
Team's site tracker, note of 2026-08-28
Southern half was sold for housing last year; roughly 700 m² remains. Good first call with the owner, sending heads of terms.
Council and neighbours10 / 10
Supportive
Field note, 2026-08-28
Council planning committee minutes record support for local storage on this plot.
Flood risk15 / 15
No flood zone recorded
Land registry record, 2017-02-11
Usable land0 / 10
700 m²
Field note: 2026-08-28 overrides registry 2400 m² (2017-02-11)
roughly 700 m² remains
Pellick Lane Plot
45/100
S-024 · 100 if everything checks out
Left out: not enough evidence
It has one of the strongest grid figures (5 MW, 0.6 km away). But there is no land registry record and no field note, so we don't know the owner, the plot size, the flood risk or local opinion. Worth a visit, not a pitch.
Full breakdown
Spare grid capacity30 / 30
5 MW
Grid operator, as of 2026-06-30
Distance to substation15 / 15
0.6 km
Grid operator, as of 2026-06-30
Landowner0 / 20
Unknown
no owner status in notes
Council and neighbours0 / 10
Unknown
no council/community note
Flood risk0 / 15
Unknown
parcel not in land registry
Usable land0 / 10
Unknown
parcel not in land registry
How sure we are
"6/6 known" means every part of the rubric has a value from a source. It does not mean the site is confirmed feasible. None of these sites has had a feasibility study; that is exactly what the sponsor would pay for.
Grid figures are the official ones, published quarterly (these are from June 2026).
Letters of intent are non-binding.
The notes on council and neighbours are the team's own reports.
Where a figure was missing we scored it zero, not an average. "If everything checks out" assumes missing parts get full marks; known values stay as they are.